Nuclear Reactors Built with Foreign Collaboration
The details
pertaining to under construction nuclear reactors is tabulated below:
Name of the
Project
|
Location
|
Capacity
(MW)
|
Approved
Cost (Rs. in
crores)
|
Status
|
Projects
under Construction / Commissioning
|
||||
Indigenous
Nuclear Power Project(s)
|
||||
Kakrapar Atomic
Power Project
(KAPP)-3&4
|
Kakrapar,
Gujarat
|
2X700
|
11459
|
Under
various stages of
construction.
Expected
completion by
2018/19
|
Rajasthan
Atomic
Power
Project
(RAPP)-
7&8
|
Rawatbhata,
Rajasthan
|
2X700
|
12320
|
|
Nuclear
Power Project(s) with foreign technical cooperation
|
||||
Kudankulam
Nuclear
Power
Plant (KKNPP)-2
|
Kudankulam,
Tamil
Nadu
|
1000
|
17270*
|
Reactor
attained first
criticality
on July 10, 2016.
Expected
to start
commercial
operation in
current
year -2016.
|
Projects
Accorded Financial Sanction
|
||||
Indigenous
Nuclear Power Project(s)
|
||||
Gorakhpur
Haryana
Anu
Vidyut
Pariyojna
(GHAVP)
-1&2
|
Gorakhpur,
Haryana
|
2X700
|
20594
|
Work
has started.
Expected
completion by
2023/24.
|
Nuclear
Power Project(s) with foreign technical cooperation
|
||||
Kudankulam
Nuclear
Power
Plant (KKNPP)-
3&4
|
Kudankulam,
Tamil
Nadu
|
2X1000
|
39849
|
Excavation
work
commenced.
Expected
completion
by
2023/24.
|
* Cost for
KKNPP-1&2, It is under revision to Rs. 22462 crore
Bharatiya Nabhikiya Vidyut Nigam
Limited (BHAVINI), a public sector company under Department of Atomic Energy
(DAE) is constructing one 500 MW Prototype Fast Breeder Reactor (PFBR) at
Kalpakkam, Tamil Nadu. The design and construction of PFBR is fully indigenous.
The project is being built with a total cost of Rs 5677 Cr. Construction of
this reactor is completed and commissioning is in advanced stage. The reactor
is expected to achieve its first criticality by next year.