16 July 2015

Dreadnought of Dedicated Freight corridors shaping up; Rs 81,459 Crore approval perk up work

Goods laden rakes running on dedicated corridors, sparing over burdened tracks for back-to-back swanky passenger trains filing fast solar energy-lit Swachch  stations and smart cities in large swathes of the populous nation within next  four years sounds like castles in air.
But many people are fairly sanguine that green shoots are sprouted. Rs 15,500 crore contracts were given in the past few months by the Dedicated Freight Corridor Corporation Limited  (DFCCL), and heavy machineries in large numbers are being moved on the ground to  expedite the gigantic task which, for an example, is guzzling Rs 100 crore per  month on the Khurja –Kanpur section alone against earlier investment of Rs.30  crore per month.
As deadlines loom, the fourth floor of five-storey  building next to Pragati Maidan appears peaceful, but massive churning is  underway with pre-bidding conferences notices on display boards and bureaucrats  collating data from ground as the Rail Bhawan mounts continued surveillance on  the progress. The building and the Corporation logo do not draw attention which  is more focused on attractive stalls of sprawling exhibition ground but on  ground locals say development is palpable.
“An analysis of the  ordering progress by DFCCIL in the recent months reveal that the total value of  contracts awarded since November is a whopping Rs 15,485 crore which is more than  total works awarded by the sameorganisation in the past six years, that stands  at Rs.13,125 crore” said officials flipping through piles of data sheets and  browsing on computers.
Most of these contracts are for the construction of track and structures and electrical and  signalling installations on the Western and Eastern Freight  corridors. During the past few months, major contracts issued comprise civil contracts from Kanpur-Mughalsarai ( 402 kms) and Vadodara to Vaitarna  ( 320 kms), electrical and signallingcontracts on western DFC from Rewari to  Vadodara ( 950 kms).
 Officials feel that the two DFCs would free up 70 per cent of railways cargo carrying capacity, but land acquisition challenges face the iconic project.This is despite the fact that 84 per cent of land  acquisitions have been completed in both the corridors-including 88 per cent in  the Western corridor and 79 per cent in the eastern corridor. Sixteen per cent is hanging fire, awaiting the new land laws.
 According to DFCCIL  sources, there are 1,042 court cases and 3,391 arbitration disputes pending as  land losers have knocked courts' doors.As a consequence, land is not available  in 144 patches, affecting length of 245kms in eastern corridor and 296  stretches impacting 113 kms in the western corridor. These patches are mainly in UP, Bihar, Maharashtra , Haryana and Gujarat.
DFCCIL's Adesh  Sharma says work is underway in full swing and now per day 80,000 cubic meter  earth work is done against earlier data of 5000 cubic meter per day. Contractors,  he said, had been directed to deploy two times in volumes the mandatory  machineries ,More than 100 excavators are working in each corridor. December 2019 is the date line for completion based on the land acquisition status and contracts position.
 Officials feel the Khurja-Kanpur will be ready by March 2018; DurgawatiSasaram during the current fiscal, Mughalsarai-Sonnagar by 2017 and Kanpur-Mughalsarai by December 2018.   Likewise in the Western corridorRewari-Iqbalgar has been planned for June 2018, Iqbalgarh-Vadodara by March 2019. The revenue will start trickling due to phased commissioning of corridors as the access charges will be levied. Mr Sharma has told media that multi-modal logistic parks and private freight terminals, to be developed along the DFCs, will impart additional income track access charges which are being calculated by an expert committee.
Flagging big ticket procurements finalised by the DFCCIL, officials claim that after a long period stagnation, riddled with procurement snags and procedural delays, both the corridors, being built by the corporation, an SPV ( Special Purpose Vehicle) of Railway Ministry have now started gathering momentum.
The National Democratic Alliance (NDA) government, last week, approved the revised cost estimate (RCE) of Rs.81,459 crore for both the corridors and the  much awaited sanction has perked up things in the infra project. Of this  amount, construction cost accounts for Rs.26,674 crores for the EDFC and  Rs.46,718 crores for the WDFC and land acquisition cost of Rs.8,067  crore.
The Corporation, recalling previous handicaps, says that the  original estimate prepared by RITES in 2007 had to undergo many major changes as  it had no provision of soft costs ( about Rs.27,381 crore like interest during  construction ,insurance ,escalation and other contingencies. The estimate, they say, had no provision even for the basic electrification of WDFC and was devoid  of the latest specifications already in vogue on word Railways. 
Subsequently, during the revision, the standard of construction was raised from 25 ton axle load to 32.5 ton and a slew of advanced safety features  including Train Protection Warning System (TPWS) have been incorporated. 
Oblivious of these developments, passengers on trains debate on the corridors. A UNI correspondent, travelling on a Shatabdi train to Kanpur recently found travellers discussing large tracks of blanketing near Tundala .  While a few passengers feigned ignorance, others said parallel highway is being  made but other quipped, ”come what may ,something is happening”.
An  informed railway staffer briefed them about the DFC ,but it evoked interesting  comments from sceptics - these announcements of flagship programmes are all  humbug and ”we are being bamboozled for make believe world”.
Twirling  his moustache, a passenger commented that these projects should not be linked  with party politics and such iconic programmes be appreciated– started by the  previous United Progressive Alliance regime and expedited by the NDA  dispensation as finally these will be national assets in a few years. Every project starts like these and one day dreadnoughts emerge in skylines.
The Western DFC is being funded by Japan International Cooperation Agency (JICA). Part of  Eastern DFC (Mughalsarai-Allahabad-Kanpur- Khurja –Ludhiana ) is being  funded by World Bank. Danduni –Sonnagar section of the Eastern DFC will be through PPP. East west Corridor ( Kolkata-Mumbai) 2,330 kms,  North–South corridor, 2343 km, East West Corridor  (  Kharagpur-Vijayawada ) 1,100km and Southern Corridor ( Chennai-Goa) 899 kms are  on slate as future corridors.
DFCCIL appears conceived for the development of dedicated freight line to boost freight transportation in Railways which will spur Railway share in transportation of goods. The dedicate Freight corridors were necessitated after saturation of Golden Quadrilateral (  which had linked four metros Delhi, Chennai, Howarh, Mumbai along with diagonals  Delhi-Chennai and Mumbai–Howrah)-with over 10,000 kms and carrying more than 55  per cent revenue earning freight traffic. In wake of the bulging traffic, the Government planned two Corridors--- the Western DFC ( 1,502 kms) and Eastern DFC (  1,840 km)----sparing a total length of about 3,342 route km.
The EDFC, starting from Dankuni in West Bengal, will pass through the states of Jharkhand, Bihar, Uttar Pradesh and Haryana to terminate at Ludhiana. The Western corridor that will traverse the distance from Dadri(UP) to Mumbai–Jawaharlal Nehru) Port ( JNPT) will traverse the National Capital Region,  Haryana, Rajasthan, Gujarat and Maharashtra.
 Envisioning paradigm shift in the freight operation , the DFCs envisage long haul operation;trailing  loads per train will increase from 5,000 to 13,000 tonnes. On the  ground, works are on, but the Land Bill passage is all set to play pivotal role  as the land acquisition is caught in legal wrangles. Civil works on Bhaupur-Khurja section is progressing well .The earth work for 150 kms formation  and blanketing has been completed in 55 kms.
Likewise, civil works in Rewari-Iqbalgarh for 625 kms have been started. Work on embankments is in progress in about 150 kms and work on 70 minor bridges also got off. In Mughalsari –Sonnagar section 65 m long bow string girder for new road  overbridge at Bhabua was successfuly launched across three Indian Railway (IR)  tracks a few months ago.

No comments:

Post a Comment

Featured post

UKPCS2012 FINAL RESULT SAMVEG IAS DEHRADUN

    Heartfelt congratulations to all my dear student .this was outstanding performance .this was possible due to ...