Presently, following nuclear power projects are under various stages of construction:
Project
|
Location & State
|
Capacity(MW)
|
KAPP-3&4
|
Kakrapar, Gujarat
|
2 x 700
|
RAPP-7&8
|
Rawatbhata, Rajasthan
|
2 x 700
|
KKNPP– 3&4
|
Kudankulam, Tamil Nadu
|
2 x 1000
|
PFBR
|
Kalpakkam, Tamil Nadu
|
500
|
GHAVP-1&2
|
Gorakhpur, Haryana
|
2 x 700
|
In addition, following nuclear power projects have been accorded financial sanction and administrative approval by the Government:
Project
|
Location & State
|
Capacity(MW)
|
Projects Accorded Administrative Approval & Financial Sanction
| ||
GHAVP-3&4
|
Gorakhpur, Haryana
|
2 x 700
|
Kaiga-5&6
|
Kaiga, Karnataka
|
2 x 700
|
Chutka-1&2
|
Chutka, Madhya Pradesh
|
2 x 700
|
Mahi Banswara-1 to 4
|
Mahi Banswara, Rajasthan
|
4 x 700
|
KKNPP-5&6
|
Kudankulam, Tamil Nadu
|
2 x 1000
|
The Government has also accorded ‘In principle’ approval of the following sites for setting up nuclear power plants in future.
Sites Accorded ‘In-Principle’ Approval
| ||
Bhimpur, Units-1 to 4
|
Bhimpur, Madhya Pradesh
|
4 x 700
|
Jaitapur, Units-1 to 6
|
Jaitapur, Maharashtra
|
6 x 1650
|
Kovvada, Units-1 to 6
|
Kovvada, Andhra Pradesh
|
6 x 1208
|
Chhaya Mithi Virdi, Units-1 to 6
|
Chhaya Mithi Virdi, Gujarat
|
6 x 1000*
|
Haripur, Units-1 to 6
|
Haripur, West Bengal
|
6 x 1000*
|
*Nominal Capacity
On completion of the projects presently under construction and accorded financial sanction, the installed nuclear power capacity is expected to reach 10080 MW by 2020 and over 20000 MW by 2031.